- Pre-application
conference with the Zoning Administrator for Minor & Major Subdivisions.
- Applicant submits
application, narrative, and fees to Zoning Administrator.
- Applicant submits
25 prints of the preliminary layout as a preliminary plat to Zoning
Administrator. Including all items stated in Land Subdivision and Development
Ordinance Section 4-20.3 (A) Requirements for RPA
lots
- The Zoning
Administrator shall notify all adjoining landowners of the proposed
minor or major subdivision prior to the first Planning Commission meeting
that reviews the preliminary plat.
- The subdivider
shall then be advised within 60 days concerning any additional data
that may be required, the character and extent of public improvements
that will have to be made, and estimate of the cost of construction
or improvements and the amount of the performance bond which will be
required as a prerequisite to approval of the final subdivision plat.
- The Zoning
Administrator prepares analysis for Planning Commission and Board of
Supervisors.
- Planning Commission
reviews application. Planning Commission shall hold a Public Hearing
in accordance with Title 15,2-2204 and 15.2-2285, Code of VA (The Planning
Commission and Board of Supervisors may hold a joint Public Hearing).
Public Notice being given in accordance with above Code section. Notice
shall also include the posting of a sign on subject property.
- Following the
Public Hearing, the Planning Commission shall submit its recommendations
to the Board of Supervisors. Planning Commission shall state its reasons
for its recommendations.
- Planning Commission
shall make its recommendation to the Board of Supervisors within 90
days following the first meeting of the Planning Commission after the
proposed minor/major subdivision had been referred to the Commission.
- Board of Supervisors
shall give notice and hold a Public Hearing on the application. Board
of Supervisors may make appropriate changes or corrections in the proposed
minor/major subdivision. The Board of Supervisors may approve or disapprove
the minor/major subdivision. Time limit for action by the Board of Supervisors
is 12 months.
- Upon approval
of preliminary plan of minor/major subdivision, applicant submits final
minor/major subdivision plan to Zoning Administrator within 6 months.
- Zoning Administrator
has 90 days to approve the final site plan. Approval of final site plan
expires in 1 year.
Family
Subdivision Affidavit - Required for Family Subdivisions and must
be submitted with the plat/survey.
Zoning
Fees
Land
Development Application This form is in Acrobat (pdf) format.